All content in this website is sourced legitimately

Page No: 1
Rs 1500 crore NPK plant: Three in the race
Nov 07: NPK Fertilizer Greenfield Project: Three contractors in the race
8Cost - Rs 1517 Crore
8Project Description: Three EPC contractors are in the race for a greenfield NPK Fertilizer unit with a capacity 1200000 MTPA of Kribhco & OCP Group in India. The Project Management Consultant is PDIL.The techno-commercial discussion has been completed and price bids are to be opened. The equipment requirements are Feeding hoppers, Electronic belt scales, Conveyors, Mixers, Crushers, Granulators, Dryers, Feeders, Coolers, Elevators, Blowers, Collectors, Towers, Chimneys, Drums, Bins, Screens and more
8
Project Event: The EPC contractor is to be selected by January 2018 against a tender floated in February 2017. Tender for equipment's and services is likely to be released in March 2018 Click here for more information
SSP/ Sulphuric Acid Annual Maintenance Project  
8Cost - Rs 0.30 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in May or June 2018 at their existing fertilizer complex at Palghar in Maharashtra. The existing capacity is made up of 231000 MTPA of SSP, 33000 MTPA of Sulphuric acid. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for the annual maintenance contractor is likely to be released in March or April 2018Click here for more information
NPK Fertilizer Annual Maintenance Project 

8Cost - Rs 0.15 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in August or September 2018 at their existing fertilizer complex at Latur in Maharashtra. The existing capacity is made up of 25000 MTPA of NPK. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for the Annual Maintenance Contractor is likely to be released in Aprill or May 2018
 Click here for more information


**********************************

Back  |  Top