Software Updates : Power Projects
Nov 03: 8Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs 300 crore
8Project Description: The owner is scheduled to install an FGD for a 600 MW unit at it's 1440 MW (4*210+1*600 MW) thermal power plant. The company is expected to float tenders for the same. At present, feasibility studies and phasing plans are ongoing. The project is expected to kick off in late 2020. RFQ for supply and installation of FGD are expected to be out by the fourth quarter of 2018. 
8The major requirement will be FGD, stacker and reclaimer, earth work, cranes, pipes, installation, gypsum disposal, wet lime among others.
8Project Event: RFQs for supply and installation of FGD are expected to be out by the Q4 2018.
8Expenditure Approval: Q3:2018
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q4:2020
8Completion Date: Q2:2023
Click here for more information
8Project Name: Gas Power Station Maintenance Project
8Project Cost: Rs 30 crore
8Project Description: The developer has planned a 35-days scheduled maintenance of Steam Turbine - II (154.51 MW) in the 817 MW (4x130.19 MW GT + 2x154.51 MW ST) Gas Based Power Station covering annual inspection of steam turbine, and renovation and modernization of C&I equipment which includes overhauling of auxiliary parts of C&I equipment. There will be a technology up-gradation in the DCS system of Seimens T3000. 
8Equipment required will be console, display panels, sensors, turbine-generator bearings, casings, valves, filters, among others.
8Project Event: RFQs for equipment required for maintenance are expected by fourth week of November 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 28/Nov/2017
8Release Date: Dec/2017
8Start Date: 15/Jan/2018
8Completion Date: 18/Feb/2018
Click here for more information


**********************************