Software Updates : Power Projects
Nov 01: 8Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs 500 crore
8Project Description: The owner  is scheduled to install FGDs for Units 3 and 4 at it's 2000 MW (4x500 MW) thermal power plant. The company is expected to float tenders for the same. At present, feasibility studies and phasing plans are underway. The project is expected to kick off in late 2022. RFQs for supply and installation of FGDs are expected to be out by the fourth quarter of 2018. 
8The major requirement will be FGDs, stacker and reclaimer, earth work, cranes, pipes, installation, gypsum disposal, wet lime among others.
8Project Event: RFQs for supply and installation of FGDs are expected to be out by the Q4 2018.
8Expenditure Approval: Q2:2018
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q4:2022
8Completion Date: Q2:2025
Click here for more information
8Project Name: Hydroelectric Greenfield Project
8Project Cost: Rs 4900 crore
8Project Description: The owner is carrying out the contracting activities for the 560 MW (4*140 MW) Hydroelectric Power Station. The company has already floated the contract for civil works in August 2017. However, to encourage bidder participation in the civil works package, the last date was extended and the HM & EM packages will now come out after the civil contract order is placed.
8Project Event: RFQs for hydro-mechanical works are likely to be floated in the first week of November 2017.
8Expenditure Approval: Sep/2014
8RFQ Date: 4/Nov/2017
8Release Date: Jan/2018
8Start Date: Jun/2018
8Completion Date: Jan/2024
Click here for more information


**********************************