Software updates: Oil and Gas Projects.
Oct 27: 8Project Name: Refinery Debottlenecking Greenfield
8Project Cost: Rs 2519 Crore
8Project Description: An existing company along with its EPC contractor is currently conducting basic engineering studies for a low cost debottlenecking of its refinery, raising its capacity from 6 MMTPA to 7.8 MMTPA. 
8Project Event: RFQ for listed equipment is expected by December 2017.
8Expenditure Approval: Q4:2016
8RFQ Date: Dec/2017
8Release Date: Jan/2018
8Start Date: Q2:2017
8Completion Date: Q4:2018
 Click here for more details.
8Project Name: Brownfield LPG Bottling Plant Expansion
8Project Cost: Rs 100 Crore
8Project Description: An existing company is planning to expand its LPG bottling plant capacity from 1000 MT to 2500 MT by installing new 3 X 500 MT mounded storage vessels. Environmental clearance was granted by June 2017. Some of the equipment is ordered and rest of the equipment is under tendering.
8Project Event: RFQ for Civil work is expected by December 2017.
8Expenditure Approval: Q1:2017
8RFQ Date: Nov/2017
8Release Date: Dec/2017
8Start Date: Q2:2017
8Completion Date: Q2:2019
Click here for more details.
8Project Name: Drilling Site Hydrofracturing (Proppant requirement)
8Project Description: Promoter is planning hydraulic fracturing work in its onland oil fields. The requirement from promoter's end for Hydrofracturing services will be for lightweight ceramic/sintered bauxite proppant having a preferable mesh size of 20/40 or 16/30 or 12/20 respectively. An annual requirement of 1000 MT of proppant is expected from the promoter's end.
8Project Event: RFP's for the proppant is expected by November end 2017.
8Expenditure Approval: Sep/2017
8RFQ Date: Nov/2017
8Release Date: Nov/2017
8Start Date: Q1/2018
8Completion Date: Q1/2018
Click here for more details.
8Project Name: GCS Expansion
8Project Description: Promoter has proposed the expansion of its Gas Collecting Station (GCS) from an existing 2.2 MMSCMD capacity to 2.71 MMSCMD. The main equipment requirements in this project will be:- Gas Scrubber, Gas Filter, Flare KOD, Flare Stack and Tip. The tendering process has been completed and Notice of Award (NOA) is expected in the next 15-20 days.
8Expenditure Approval: Q1/2016
8RFQ Date: Oct/2017
8Release Date: Nov/2017
8Start Date: Mar/2018
8Completion Date: May/2019
Click here for more details.


**********************************