Software Updates : Power Projects
Oct 26: 8Project Name: Hydroelectric Pumped Storage Project
8Project Cost: Rs 900 crore
8Project Description: The owner is carrying out the selection of DPR consultant activities for a 320MW (80*4) Pumped Storage Plant which envisages re-utilisation of water of the Upper Kolab reservoir which is being released from the existing 320 MW Hydroelectric Power Station. TOR has been granted on Jan 2017 and Environment Clearance is under process. Tender for a DPR consultant has been floated in August 2017 and is under scrutiny. The consultant will take 2 years to finalize the detailed project report and 6-8 months to conduct SIA, PH and R&R plans for the EIA study. The owner  will come out with an EPC contractor soon.
8Project Event: RFQ for an EPC contractor is expected by Q1 2019.
8Expenditure Approval: Q4:2018
8RFQ Date: Q1:2019
8Release Date: Q2:2019
8Start Date: Q2:2021
8Completion Date: Q4:2025
Click here for more information
8Project Name: Thermal Power Station Maintenance Project (Unit-2)
8Project Cost: Rs 18 crore
8Project Description: The developer has planned a 21 days scheduled maintenance of Unit-2 (250 MW) in the 1500 MW Thermal Power Station covering an annual maintenance of equipment which includes overhauling of auxiliary parts of turbine, boiler, condenser, generator comprising HP, IP, LP cylinders gas testing, testing and cleaning of condenser parts, Residual Life Assessment of boiler pressure parts, assessing performance and condition monitoring of furnace, mills, APH and associated ducts.
8Project Event: RFQ of an annual maintenance equipment is expected by second week of November 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 10/Nov/2017
8Release Date: 25/Nov/2017
8Start Date: 2/Jan/2018
8Completion Date: 22/Jan/2018
Click here for more information
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs 320 Crores approximately
8Project Description: The owner is scheduled to install an FGD for Units-1, 2 and 3 (2x121 MW + 120 MW) at it's 422 MW (2x30 MW + 2x121 MW + 120 MW) thermal power plant. At present, the consultant is working on the feasibility studies and the project is expected to kick off in early 2021. RFQs for supply and installation of FGDs are expected to be out by the second quarter of 2018. 
8Project Event: RFQs for supply and installation of FGDs are expected to be out by Q2, 2018.
8Expenditure Approval: 2016
8RFQ Date: Q2:2018
8Release Date: Q2:2018
8Start Date: Q1:2021
8Completion Date: Q3:2021
Click here for more information.
8Project Name: Thermal Power Station - Dismantling
8Project Cost: Rs 30 Crores approximately
8Project Description:The Operator is planning to retire and dismantle Units 15 and 16 (2x30 MW) of it's 422 MW (2x30 MW + 2x121 MW + 120 MW) thermal power plant. At present, the consultant is working on the feasibility studies, based on which action is due by the second quarter of 2018. As of now, these two units have already been shut down since May, 2017 due to low schedule. RFQs for civil work and dismantling services of various equipment are expected by the third quarter of 2018.
8Project Event:  RFQs for dismantling services of various equipment are expected by Q3, 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Q2:2018
8Release Date: Q2:2018
8Start Date:  Q3:2018
8Completion Date: Q2:2019
Click here for more information.


**********************************