Software updates: Fertilizer projects
Oct 25: SOP capacity to be raised
 
An existing company is planning to enhance the capacity of its Sulphate of Potash (SOP) unit from 300 TPD to 1200 TPD at Hajipur, Gujarat.
8The company also plans to enhance the capacity of the Co-Generation Power Plant from 10 MW to 45 MW, also set up two DG Sets with capacities of 3000 KVA and 500 KVA.
8The projected cost is Rs 500 crore.
8Speaking to this website, company sources said environmental clearance application was submitted in October and it is likely to be granted in April 2018 and RFQs for a contractor is likely to be released in December 2017.
Click on Reports for key contacts
Technical Pesticide unit coming up

8
A new company is planning to set up a greenfield Technical Pesticide proejct with a capacity 6000 MTPA in India.
8The total project investment cost is around Rs 25 crore.
8The power requirement is about 450 KVA, which will be sourced from the State Electricity Board.
8The company has also proposed to set up a DG set with capacity 225 KVA.
8The requirement of water and land is about 90 KLPD and 10,000 square meters respectively.
8The fuel requirement is about 600 Lit per hour of High-Speed Diesel and Light Diesel.
Click on Reports for key contacts
SSP/NPK Annual Maintenance Project   

8Cost - Rs 0.30 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in June or July 2018 at their existing fertilizer complex in Maharashtra. The existing capacity is made up of 120000 MTPA of SSP and 60000 MTPA of NPK. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for Annual Maintenance Contractor is likely to be released in February or March 2018
Click here for more information
 SSP Annual Maintenance Project
8Cost - Rs 0.15 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in April or May 2018 at their existing fertilizer complex at Nanded in Maharashtra. The existing capacity is made up of 20000 MTPA of SSP. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for Annual Maintenance Contractor is likely to be released in January or February 2018.
Click here for more information
 
SSP/Sulphuric Acid Annual Maintenance Project   
8Cost - Rs 0.25 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in July or August 2018 at its fertilizer complex at Gorakhpur in Uttar Pradesh. The existing capacity is made up of 66000 MTPA of SSP and 33000 MTPA of sulphuric acid. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for Annual Maintenance Contractor is likely to be released in March or April 2018.
Click here for more information  
Synthetic organic chemical unit
An existing Fertilizer & Chemical company is awaiting environmental clearance for its greenfield synthetic chemical unit in India.
8The projected investment cost is around Rs 70 crore.
 Following are the requirement of raw materials.
8Urea - 3618 MTPA
8Naphthalene- 2010 MTPA
8Nitric Acid -  2250 MTPA
8Coal- 52.5 MTPD
8HSD - 125 Lit/ hr
Click here for more information  
Rs 250 crore technical pesticide unit
A new company is planning to a greenfield technical pesticide unit with a capacity 29400 MTPA in India.
8The total project investment cost is around Rs 250 crore.
8The power requirement is about 1000 KVA, which will be sourced from State Electricity Board.
8The company has also proposed to set up 4 DG sets with a capacity 500 KVA each.
8The fuel requirement is about 500 Litre per hour of  HSD and about 262 Sm3/hr of natural gas for the Thermic fluid heater with capacity 2 Million Kcal.
8Sources said that the proposal for environmental clearance has been accepted and it is likely to be granted in December 2017 and tender for equipment and services will take a minimum 3 to 4 months subsequently.
Click on Report for more


**********************************