Software Updates: Power Projects
Oct 24:
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: Rs 420 Crores approximately
8Project Description: The Operator is scheduled to install FGDs in Unit-7 and Unit-8 (2x250 MW) of 630 MW (2x250 MW + 130 MW) thermal power plant. At present, the feasibility studies are ongoing. The project is expected to kick off by the end of March, 2023. RFQs for supply and installation of FGDs are expected to be out by the second quarter of 2018. 
8Project Event: RFQs for supply and installation of FGDs are expected to be out by the second quarter of 2018.
8Expenditure Approval: 2017
8RFQ Date: Q2:2018
8Release Date: Q4:2018
8Start Date: Mar/2023
8Completion Date: Q4:2023
Click here for more.
8Project Name: Thermal Power Station - Dismantling
8Project Cost: Rs 80 Crores approximately
8Project Description: The Operator is planning to retire and dismantle Units 1,2 and 3 of cumulative capacity 390 MW (3x130 MW) of it's coal based thermal power plant. Units 1 and 2 have already been shut down since January and August respectively and Unit 3 is expected to follow suit. Technical details of the phasing-out process is under discussion and RFQs for civil work and dismantling services of various equipment are expected by the third quarter of 2018.
8Project Event: RFQ for dismantling services of various equipment is expected by Q3, 2018.
8Expenditure Approval: 2016
8RFQ Date: Q3:2018
8Release Date: Q3:2018
8Start Date: Q1:2020
8Completion Date: Q4:2020