Software updates: Fertilizer projects
Oct 17: NPK/SSP Annual Maintenance Project 
8Cost - Rs 0.28 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in March or April 2018 at their existing fertilizer complex in India. The existing capacity is made up of 140000 MTPA of SSP, 45000 MTPA of Granular NPK mixed fertilizers, 40000 MTPA of Sulphuric acid respectively. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for a maintenance contractor is likely to be released in January 2018.
Click here for more information
SSP/NPK Annual Maintenance Project
8Cost - Rs 0.20 Crore
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in July or August 2018 at their existing fertilizer complex in India. The existing capacity is made up of 66000 MTPA of SSP, 60000 MTPA of NPK. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8Project Event: RFQs for Annual Maintenance Contractor is likely to be released in March or April 2018
Click here for more information 
New Sulphuric acid unit: Equipment needed
An existing steel manufacturing company is planning to set up a greenfield Sulphuric acid unit with a capacity 125 MTPD in India.
8The project investment cost is around Rs 0.50 crore.
8The equipment requirements are Steam Turbine Generators, Economizers, Reheaters, Boilers, Sulphur Combustor, Drying Towers,  Vapor Separators,  Converters, Absorbers, Absorber Exchangers,  Sulphur filters, Sulphuric Melting Tank, Motors, Pumps and more
Click On Report for more
Captive Power Unit Expansion Project 

8Cost - Rs 224 Crore
8Project Description: A Fertilizer company is awaiting environmental clearance for an expansion of its captive power unit from 125 MW to 141 MW in India. The equipment requirements are Turbine Generator with their Auxiliaries and Utility, Boiler House including ESP, Ash Handling and other Auxiliaries, Fuel Handling plant, Automation, Instrumentation, Electrical Installations, Civil Work equipment and more
8Project Event: Tender for a Contractor is likely to be released in November 2017.
Click here for more information
Ammonia-Urea
 Annual Maintenance Project
8Cost - Rs 25 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in June or July 2018 at their existing fertilizer complex at Kota in India. The existing capacity is made up of 650 MTPD of Ammonia, 1150 MTPD of urea. Pre-Vendor Qualification is necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in February 2018.
 
Click here for more information
SSP Annual Maintenance Project   
8Cost - Rs 0.15 Crore
8Project Description: A Fertilizer company is planning an annual shutdown maintenance in April or May 2018 at their existing fertilizer complex in India. The existing capacity is made up of 67000 MTPA of SSP. Pre-Vendor Qualification may be necessary for a maintenance contractor.
8
Project Event: Tender for a maintenance contractor is likely to be released in January 2018.
Click here for more information

**********************************

Back  |  Top