Software Updates: Power Projects
Oct 13: 8Project Name: Greenfield Multipurpose Project
8Project Cost: Rs 1500 crore
8Project Description: The developer along with PFR consultant is carrying out the site survey & investigation activities for scoping the environment clearance for a 300 MW (3*100 MW) greenfield multipurpose project. TOR was accorded on 25 January 2017. At present, PFR prepared, and has been submitted to CWC for appraisal and site survey activities are currently on. The developer will come out with an EIA consultant tender soon and after the EC is elicited, package wise contracts would come.
8Project Event: RFQ for an EIA consultant for preparation of DPR and EIA/EMP report is expected by Q1 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2018
8Release Date: Q1:2018
8Start Date: Q2:2019
8Completion Date: Q3:2024
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 680 Crores approximately
8Project Description: The developer is planning to construct a 67 MW (3*22.33 MW) Hydroelectric Project. The project is under advanced stages of DPR preparation and the owner is likely to float the RFQ for an EPC contractor by the first quarter of 2019.
8Project Event: RFQ for an EPC contractor is expected by the first quarter of 2019.
8Expenditure Approval: 2014
8RFQ Date: Q1:2019
8Release Date: Q3:2019
8Start Date: Q4:2019
8Completion Date: 2024
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 650 Crores approximately
8Project Description: The developer is planning to construct a 66 MW (3*22 MW) Hydroelectric Project. The project has obtained EC and the owner is currently accepting RFQs for the signing of PPAs. Also, RFQ for civil work and BoP is expected to be out shortly.
8Project Event: RFQ for signing of PPA is currently being accepted by the proponent and RFQs for civil work and BoP are expected to be out by second the quarter of 2018.
8Expenditure Approval: 2014
8RFQ Date: Q2:2018
8Release Date: Q4:2018
8Start Date: Q1:2019
8Completion Date: 2024
Click here for more information


**********************************