Software Updates: Power Projects
Oct 04: 8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 13500 Crores approximately
8Project Description: The owner is planning to set up a 1878 MW (28 MW + 8*231.25 MW) hydroelectric power station. TOR was initially granted to the project in June, 2014. However, due to difficulty in approaching the project site, survey and investigation is running a little behind schedule. The proponent has obtained an extension on the TOR till June, 2018, around which time they are expected to apply for EC. At present DPR preparation is ongoing along with assessment of socio-economic impact. RFQs for major equipment (turbine-generator), instrumentation and BoP (balance of plant) are expected to be out in 2018.
8Project Event: RFQs for turbine-generator (T-G), instrumentation and BoP (balance of plant) are expected to be out in the second quarter of 2018.
8Expenditure Approval: 2014
8RFQ Date: Q2:2018
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: 2024
Click here for more information
8Project Name: Greenfield Hydroelectric Project
8Project Cost: 800 crores
8Project Description: The promoter along with EIA consultant  is carrying out the EIA studies for scoping the environment clearance for a 64 MW (2*32 MW) greenfield hydel project. TOR has been accorded on 5th September 2016 which would be valid for five years. Baesline studies has been approved by Government of Uttarakhand and CEA. DPR has been prepared by Indo Canadian Consutancy Services Limited. EIA studies are ongoing in which public hearing, socio-economic aspects and wildlife clearance are still pending. The owner will float package-wise contracts after getting EC.
8Project Event: RFQ for civil package is expected by 3rd quarter of 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q4:2018
8Start Date: Q1:2019
8Completion Date: Q2:2024
Click here for more information


**********************************