Aug 30: 8Project Name: GCS, Treatment Facility and Development Drilling 8Project Cost: Rs 758 crore 8Project Description: Operator is planning development drilling of 30 wells. The project also involves the construction of a GCS and the laying of a pipeline from GCS to offtake centre. The contracts for GCS and pipelines have been awarded but the operator will come up awards for development drilling. Further RFQs are expected shortly. 8Expenditure Approval: Q2:2015 8RFQ Date: Mar/2018 8Release Date: May/2018 8Start Date: Jun/2018 8Completion Date: 2018 Click here for more details. 8Project Name: White Oil Storage Tank Project 8Project Cost: Rs 800 crore 8Project Description: A owner along with EPCM contractor is carrying out construction activities to install a product storage tanks for White Oil products 8Project Event: RFQs for Mechanical work (Erection & Installation) is expected by October 2017. 8Expenditure Approval: Q1/2016 8RFQ Date: Oct/2017 8Release Date: Nov/2017 8Start Date: Q2:2016 8Completion Date: Q2:2018 Click here for more details.