Software updates: Power projects
Aug 29: 8Project Name: Hydroelectric Project
8Project Cost: Rs 287 Crores
8Project Description: A JV company along with its consultant is writing out the final EIA report for scoping environment clearance for a 52 MW (2*26 MW) hydel project. TOR has been granted on 12th February 2015. Project Proponent has submitted the EIA report on 11th June 2017 for EAC clearance but due to the baseline data being older more than 3 years, it has been deferred for next meeting. Environment Clearance is likely to be elicited by 4th Quarter of 2017. Project kick off date is expected by 2nd Quarter of 2018. 
8Major equipment that will be required will be two Francis Turbine, Radial gates, turbine-generator sets and associated auxiliaries, transformers, butterfly valves, turbine auxiliaries, governors with auxiliaries, cables, bus ducts and terminal equipment, EOT cranes, shaft and bearing, couplings, vibration control system, girders, tunnel boring machine, powerhouse equipment among others.
8Project Event: RFQ for civil works are expected by 1st Quarter of 2018 while those for electro-mechanical and hydro-mechanical works will be out subsequently after a month.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2018
8Release Date: Q1:2018
8Start Date: Q2:2018
8Completion Date: Q4:2022
Click here for more information, including key contacts and other project parameters.
8Project Name: Power Plant Expansion
8Project Cost: Rs 2836 Crores
8Project Description: The owner is planning to add a 1*350 MW coal based thermal plant to it's existing complex. TOR is expected in a couple of months and shortly after that, there is going to be a requirement for hiring an EIA consultant approximately by the last quarter of 2018. RFQs for Civil works worth Rs 93 crores, Electrical package worth Rs 33 crores, Mechanical package worth Rs 510 crores, Control and Instrumentation package worth Rs 19 crores and BoP equipment are expected to start coming in from the last quarter of 2018. It is to be noted that the BTG package will be open to international bidding whereas the BoP will be open to domestic competitive bidding. 
The major requirement will be land levelling, condenser, cooling tower, boiler (outdoor, supercritical once through, balanced draft type with single reheat, direct pulverised coal fired and membrane water tube type structure), boiler auxiliaries, steam turbine (multistage i.e single reheat, regenerative, suitable for indoor installation), regenerative feed heating system (LP heater, direct contact type deaerating heater, HP heater), governor and control unit, ash handling plant. ESP (electrostatic precipitator), ducts, cooling water system, FGD (flue gas desulphurization) unit, fuel oil handling system, pumps, valves among others.
8Project Event: RFQ for Civil and Mechanical package is expected to be out in the first quarter of 2019.
8Expenditure Approval: 2015
8RFQ Date: Q1:2019
8Release Date: Q2:2019
8Start Date: Q2:2020
8Completion Date: 2024
Click here to access our project monitoring software

8Project Name: Greenfield Hydroelectric Power Station
8Project Cost: Rs 550 Crores
8Project Description: The owner is planning to set up a 78 MW hydel plant. TOR was granted in 2012 and at present, the DPR is being finalized. An application for EC is likely by the third quarter of 2018. RFQs are expected to be floated by the end 2018 for civil works, hydro-mechanical package, and electrical package.
Major requirement for this project will be crushers, earth-movers, tunnel boring machines, EOT cranes, turbines, turbine-generator sets, DG sets, communication system, substation, main inlet valves, butterfly valves, steel lined penstock, transmission lines, governor, and control units among others.
8Project Event: RFQ for Civil work is expected to be out in last quarter of 2018.
8Expenditure Approval: 2014
8RFQ Date: Q4:2018
8Release Date: Q4:2018
8Start Date: 2019
8Completion Date: 2020
Click here to access key contacts, a deal can just be a phone call away for you

8Project Name: Greenfield Hydroelectric Power Station
8Project Cost: Rs 2536 crore
8Project Description: The owner is planning to set up a 300 MW (4*75 MW) hydel plant. The project was granted TOR in December 2015. At present DPR preparation and surveys are ongoing. The proponents are expected to float RFQs for Civil works, Hydro-Mechanical equipment, Electrical equipment and BoP in the last quarter of 2018. Major requirements are going to be four Francis turbines, turbine-generator sets (with vertical shaft), piping and flanges, valves, control cabinet, 11kV bus duct system along with auxiliary components, 400 kV GIS switchgear and 400 kV XLPE cables, vacuum circuit breakers, LT panels , PLCC systems, D.C. supply system (batteries, battery chargers and DC distribution boards), cooling water circulation system, fire protection systems, compressed air system, submersible type pumps, ventilation & air conditioning system (i.e blower, ventilation duct along with air conditioning system), oil purification system, lift, communication system and transmission system among other.
8Project Event: RFQ for Civil works expected in the last quarter of 2018.
8Expenditure Approval: 2014
8RFQ Date: Q4:2018
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: 2024
Click here for more information

8Project Name: Captive Plant Expansion
8Project Cost: Rs 160 Crores
8Project Description: A cement company is planning to expand its coal based captive power plant from 10 MW to 40 MW. Site specific geotechnical and sub-surface investigations have already been carried out and TOR is expected shortly. Thereafter there shall be a requirement for hiring an EIA consultant. RFQs for Electro-Mechanical equipment and BoP is expected to be out next year.
The major requirement will be Atmospheric Fluidized Bed Combustion (AFBC) boiler, boiler auxiliaries (including ID and FD fans, ducts) pollution control equipment (ESP/Bag houses) and other necessary valves, piping and fittings steam turbine and control room (including cable cellar, switchgear room, central control room), turbine-generator, water cooled condenser, coal crusher, conveyor and drives for coal handling plant among others.
8Project Event: RFQs for Electro-Mechanical equipment is expected to be in the third quarter of 2018.
8Expenditure Approval: 2016
8RFQ Date: Q3:2018
8Release Date: Q1:2019
8Start Date: Q3:2019
8Completion Date: 2023