Aug 24: 8Cost: Rs 500 Crore 8Project Description: A fertilizer company is awaiting capital approval for its ammonia-urea expansion project. The company will also set up a new Captive Power Plant with a capacity 95 MW. 8The equipment requirements are Compressors, Turbines, Exchangers, Vaporizers, Subcoolers, Filters, Pumps, Heaters, Towers, Vessels, Storage systems, Cooler, Furnaces, Stacks, Converters, Boilers, Drums, Blowers, Economizers, Preheaters, Reactors, Tanks, Reactors, Evaporators, Condensers, Separators, Ejectors, Absorbers, Prilling towers, Absorbers, Heat exchangers, Columns Generators and more 8Project Event: RFQs for LSTK contractor is likely to be released in November 2017 Click here for more information 8Project: Ammonia-Urea Energy Saving Project 8Cost: Rs 347 Crore 8Project Description: The owner is planning to reduce the energy consumption of Ammonia and Urea units from 8.20 Gcal/MT to 7.70 Gcal/MT and 5.79 Gcal/MT to 5.33 Gcal/MT respectively. There is also as 30 MW of Captive Power Plant in the complex. 8The equipment requirements are Process Air Compressor (PAC), Gas Turbine, Heat Recovery Steam Generation, Pumps, Pipes, among others 8Project Event: Tender for LSTK contractor is likely to be released in September 2017 Click here to go to our software