Aug 21: 8Project Name: Exploratory Drilling
8Project Cost: Rs 456 crore
8Project Description: A company is planning exploratory drilling of 10 wells at an average depth of 4000 m. The environment clearance for the project can be expected by Q1 2018. The forest clearance for the project has not been submitted as yet as well. The project will also involve use of a mobile effluent treatment plant. 
8The rig used will be a land rig or a mobile land rig of a smaller capacity. The conductor, casing and the liner pipe sizes will be 20'', (13.375'', 9.625'', 7'') and 5'' inch respectively. Civil works on the site would involve Earthwork, Surface Drainage, Fuel and Chemical Storage Area, Disposal System, Storage and Disposal Pits. The mechanical equipment required would be Pump Skid, Degasser Skid, Hopper Skid, HSD Transfer Skid, Diesel Gensets, Super Charger Skid, Wellhead and Christmas Tree. RFQs for Civil Contractor are also expected to be released Q1 2018.
8Project Event: RFQs for the rigs are expected by the January 2018.
8Expenditure Approval: Q3 2015.
8RFQ Date: Jan/2018.
8Release Date: Feb/2018.
8Start Date: Mar/2018.
8Completion Date: Q1 2021.
Click here to access more details in our software
8Project Name: Refinery Modernization Project
8Project Cost: 21000 Crore
8Project Description: The owner, PMC and licensor are together carrying out engineering activities to expand the capacity of a refinery.
At present, the project is construction work is going on.
8Major equipment required going ahead will be: flanges, valves, strippers, motors, reformer tubes, foot valves, auto recirculation valve, amine cartridge filters, torque wrenches, level switches, thermocouples, thermowells, antifriction bearing, transformer, heat tracing system, spray nozzle, columns, heat tracing system, tube inserts, bolt tensioners.
8Project Event: RFQs for short lead item is expected by October 2017.
8Expenditure Approval: Feb/2017
8RFQ Date: Oct/2017
8Release Date: Dec/2017
8Start Date: Q2/2017
8Completion Date: Q2/2020