Aug 04: 8GCS Expansion 8Project Description: An expansion of a GCS facility is planned by an E&P company. 8The main equipment requirements in this project will be:- Gas Scrubber, Gas Filter, Flare KOD, Flare Stack and Tip. 8Project Event: RFQs for the mechanical equipment is expected in the month of October 2017. 8RFQ Date: Nov/2017 8Release Date: Jan/2018 8Start Date: Mar/2018 8Completion Date: May/2019 Click here to go to our software 8Brownfield Refinery Expansion 8Project Cost: Rs 3886 8Project Description: Owner along with PMC-cum-EPCM contractor is carrying out engineering activities to expand refinery capacity by 2 MMTPA. Environmental Clearance was granted on 31 January 2017. At present, Civil work is going on. 8Major equipment required are: vessels, columns, heaters, air cooled heat exchangers, pumps, strainers, air preheaters, shell & tube heat exchangers, compressors, ejectors, fired heaters, fans, filters, feed mixers, naphtha superheater, air coolers, blowers, reactors, flame arresters, motor operated valves, reflux drum, strippers, regenerators, condensers, valves. 8Project Event: RFQs for mechanical works are expected by September 2017. 8Expenditure Approval: Q4:2016 8RFQ Date: Sep/2017 8Release Date: Nov/2017 8Start Date: Jan/2017 8Completion Date: May/2019 Click here to go to our software