Software update-III: RFQs for onshore LNG terminal equipment in September
Aug 02: An EPC contractor is currently under selection for an onshore LNG terminal in India
8Cost of the project: Over Rs 5000 crore
8EIL had done the FEED and at present, EPC contractor selection process is under progress. Major equipment required are: boil off gas compressor, high pressure LNG pump, gas engine generator, tube LNG vaporizer with air heater and submerged combustion LNG vaporizer, among others.
Project Event:  RFQs for major equipment are expected to be floated by the selected EPC contractor by September, 2017.
Expenditure Approval: Q1:2017
RFQ Date: Sep/2017
Release Date: Nov/2017
Start Date: Q4:2017
Completion Date: Q2:2019