Business Opportunity Updates
Mar 24:  Environment clearance was granted last week for installation of a Gasoline Hydro treating Unit in a refinery
8Site work has now begun.
-- Cost of the project will be Rs.554 Crore.
-- Capacity of this unit will be 0.9 MMTPA.
8Maintenance Shutdown in a refinery
-- A big 25-day shutdown is beginning April 17, 2017
8LPG bottling plant coming up: Rs 142 crore investment
-- RGQs in May, 2017