Gas pipeline project: LOA in April-May, 2017
Feb 15: The owner has further extended the last date for submission of bids to supply, lay and construct Phase I of a Gas Pipeline Project along with associated facilities.
8The LOA will be granted in April-May,2017.
8The tenders are expected to be floated in April-May,2017 for the following services and equipments:
--Pumps
--Firefighting facilities
--Electrical system
--Pipes 
--Welding materials
--Mix Concrete 
--Cranes
--Truck Trailers
--Dozers
--Excavators
--DG sets
--IP Stations
--Compressor
--Valve
--Tanks
--Line pipes
8The construction phase is expected in Q-3,2017. 
8The capacity of the natural gas pipeline is estimated to be around 90 mmscmd.
8The commissioning of the pipeline is expected in Q-3,2018.

**********************************