Feb 15: The owner has further extended the last date for submission of bids to supply, lay and construct Phase I of a Gas Pipeline Project along with associated facilities. 8The LOA will be granted in April-May,2017. 8The tenders are expected to be floated in April-May,2017 for the following services and equipments: --Pumps --Firefighting facilities --Electrical system --Pipes --Welding materials --Mix Concrete --Cranes --Truck Trailers --Dozers --Excavators --DG sets --IP Stations --Compressor --Valve --Tanks --Line pipes 8The construction phase is expected in Q-3,2017. 8The capacity of the natural gas pipeline is estimated to be around 90 mmscmd. 8The commissioning of the pipeline is expected in Q-3,2018.