New Gas Gathering Station: Cost Rs.65 crore
Jan 27: TOR has been granted on 31 Mar 2016. 
8EC is expected by end of May, 2017.
8The Expression of Interest for the project will be released by nid-February, 2017.
8Public hearing has been done for the project, but land for the pipelines is still to be acquired.
8The RFQ will be floated once the evaluation of the EOIs is finalised. 
8Equipment RFQs will be floated by the end of April 2017 and tenders will be released by June 2017.
8Currently the operator is involved in the construction of access roads for the GCS sites and buildings at the same location.