New Well to be drilled in an on-land field 
Jan 25: An oil and gas major has planned for the drilling of a new well in an on-land field for which proposal had already been submitted for clearances
8The TOR and public hearing have been done for the project:-
8The EC is expected in March, 2017.
8RFQs have begun floating already
8The tenders will be released by mid of April, 2017.
8The equipments and RFQ dates are as follows:
-- Pipeline, May, 2017
-- Manifold, May-2017.
-- Header, May-2017.
-- Piping system, May-2017.
-- Drilling Bits and Coring Bits, Feb-2017.
-- Tubular pipes and ERW pipes, Jan-2017. 
-- Drilling spools, DSA and Flanges, Feb-2017. 
8RFQs for Coring Liners, Core Barrels and Accessories will be float subsequently.