New LPG bottling plants coming up
Jan 24: Total Capacity of this new LPG plant will be 250 TMTPA.
--Total Cost of the project will be 200 crores.
--RFQs by March, 2017
Another project
Installation of 3*350 MT Mounded Storage Facility is coming up.
--PFR has been already done.
--Total Cost of the project will be Rs 20 crore.
--Time Schedule for completion of project is 28 months.