Gas collection stations and pipeline network: RFQs delayed
Jan 24: The schedule for the Installation of 5 Gas Collection Stations and the attendant pipeline network has got delayed by a few months because of the land acquisition problem in the region. 8Officials are expecting it to be sorted out in the next 2-3 months. 8New RFQ dates will be announced soon. 8Initially the RFQs will be released for booster pumps, compressors and some other critical equipments as these are long lead equipment. 8The tenders for foundation work, piling work, cementing work and the trenching work will be released by the end of March 2017. Click on Details for more