Rs 200 crore jetty modification and storage plan: RFQs for storage capacity coming up
Dec 29: Work is going on in to build storage capacity subsequent to a modification of a products handling jetty.
8The cumulative cost has been pegged at Rs 2000 crore
Project Timeline:
8The project will be commissioned in a phased manner.
8Construction of storage tanks, related utilities and infrastructures is expected to be completed by March,2020.
8As of now, jetty modification work has been completed.
The RFQ’s are expected to float for the following equipments and services as and when the expansion of terminal commences:
-- Loading arms
-- Pipelines
-- Vessels
-- Flare Stack
-- DG Sets
-- Storage Tanks- 19 Nos.
-- Safety and security Systems