Onland gas processing terminal: RFQ out
Nov 23: EPC contractors are being sought for a new gas processing terminal
8The capacity will be around 60 mmscmf
8The CGR will be of around 120 bbls/mmscf and WGR for 20 bbls/mmscfd
The following are the requirements:
8Well fluid receiving facility
8Gas cooling and separation system
8Dehydration and reclamation centre
8Hydrogen dew pointing system
8Gas export system
8Condensate stablization system
8Condensate storage and export system
8Produced water treatment centre
8Utility systems
8Power generation and distribution system
8Associated infrastructure