ONGC's unfolds big horizontal drilling programme: RFQs ahead
Sep 24: Oil and Natural Gas Corporation Limited's RFQs for the hiring of a horizontal drilling services for development drilling of 27 wells in the Bhuvanagiri & Periyakudi fields and the expansion of the Bhuvanagiri EPS liocated in the Cauvery Basin spread over the Cuddalore and Tiruvarur districts, Tamil Nadu are expected to be floated next year.
8Project Event: RFQ for the hiring of a Horizontal Drilling services is expected by Q1 2020.
RFQ for the hiring of an EPC contractor for EPS expansion is expected by Q2 2020.
Click on Details for more


**********************************

8Project Name: Development Drilling
8Project Cost: Rs 3750 crore
8Project Description: Oil and Natural Gas Corporation Limited's RFQs for the hiring of a horizontal drilling services for development drilling of 27 wells in the Bhuvanagiri & Periyakudi fields and the expansion of the Bhuvanagiri EPS liocated in the Cauvery Basin spread over the Cuddalore and Tiruvarur districts, Tamil Nadu is planned to be floated next year. The TOR for the project has been granted and the EIA report for the project will be prepared by Q1 2020 for which a tender will be floated next month. For the EPC contractor RFQs will be out at a later stage. The field development plan for the project has been approved with drilling in a phase-wise manner: 4 horizontal well drilling in Phase-1 and 13 horizontal well drilling in Phase-2 in Bhuvanagiri. Moreover, 10 well drilling programme in Periyakudi will be executed in a single phase. The drilling rig for the project will be hired on a chartered basis. The owner is soon expected to float the RFQs for the hiring of an EPC contractor for the EPS expansion. The project requirement will be Horizontal Drilling Rig, Drill Pipes, Drill Collars, Drill Bits, Casing Pipes, Blow Out Preventer (BOP), Cementing services and Drilling fluids services. Further RFQs are expected shortly.

Earlier update

Oil and Natural Gas Corporation Limited along with its Houston based consultant Blade Energy Partners is planning development drilling of 27 wells in the Bhuvanagiri & Periyakudi fields and the expansion of the Bhuvanagiri EPS liocated in the Cauvery Basin spread over the Cuddalore and Tiruvarur districts, Tamil Nadu. The field development plan for the project has already been submitted. Furthermore, the owner plans to execute the drilling in a phase-wise manner: 4 horizontal well drilling in Phase-1 and 13 horizontal well drilling in Phase-2 in Bhuvanagiri. Moreover, 10 well drilling programme in Periyakudi will be executed in a single phase. The drilling rig for the project will be hired on a chartered basis. The owner is soon expected to float the RFQs for the hiring of an EPC contractor for the EPS expansion. The project requirement will be Horizontal Drilling Rig, Drill Pipes, Drill Collars, Drill Bits, Casing Pipes, Blow Out Preventer (BOP), Cementing services and Drilling fluids services. Further RFQs are expected shortly.

8Project Event: RFQ for the hiring of a Horizontal Drilling services is expected by Q1 2020.
RFQ for the hiring of an EPC contractor for EPS expansion is expected by Q2 2020.

8Expenditure Approval: Q4/2018
8RFQ Date: Q1/2020
8Release Date: Q1/2020
8Start Date: Q4/2020
8Completion Date: Q4/2024
Click here for more details