Software update: Fertilizer projects
Jun 21: Ammonia-Urea Brownfield Project
8Cost: 6000 Cr.
8Project EventRFQ for Civil, Structural & Electrical work for truck parking been out and bid due date is 23 June 2022. The project is likely to be commissioned in September 2022 in place of June 2022 due to the slow progress.96% of construction work has been completed, construction of the bagging building has been completed. RITES is still in the process of laying rail tracks and electrifying them. Testing of one of the boilers has also been successfully completed.
Phosphoric acid Expansion Project
8Cost: 50 Cr.
8Project Event: The proposal for the term of references has been accepted and the final EIA report preparation is still ongoing, proposal for the environmental clearance is likely to be submitted in Q2 FY 2022-2023. The company is planning to hire a local contractor. RFQ for the Contractor is likely to be released in Q2 FY 2022-2023.

**********************************