Jun 16: Urea Revamp Project
8Cost: 700 Cr.
8Project EventFact Engineering and Design has been hired as the consultant. RFQ for LSTK contractor is likely to be released at the end of July 2022.
Ammonium Nitrate Greenfield Project
8Cost: 1750 Cr.
8Project Event: 30% erection has been completed, and installation is likely to be started in August 2022. Procurement of long-lead items is still ongoing, Casale has been hired as the Technology Licensor, The project is likely to be commissioned in August 2024.

**********************************