Software update: Power projects
Jun 16: Construction of 765 kV D/C Transmission Line : RFQ ahead
8
Fabrication works for lattice tower erection is in an advanced stage for completion
8Land acquisition completed for S/S works
8RFQ for the 765 kV P/S package is likely to be floated in July 2022.
Rs 4500 crore thermal power station brownfield project
870% of erection and installation of BTG works are completed.
8Railway sliding works are in the initial phase of their construction
8 RFQ for the C& I system package is likely to be floated in Q3 2022
Rs 900 crore greenfield hydroelectric project
8
EIA studies are in progress
8 The hydrology report is yet to be completed.
8Forest clearance stage-1 is pending at the nodal office.
8Civil works package(Lot-1) is expected soon.
Rs 800 crore greenfield hydroelectric project : RFQ Ahead
8Bids evaluations are in progress for civil works
8Find out who are the major contenders in the same package
8HM works package expected soon.

**********************************