Jun 16: Construction of 765 kV D/C Transmission Line : RFQ ahead 8Fabrication works for lattice tower erection is in an advanced stage for completion 8Land acquisition completed for S/S works 8RFQ for the 765 kV P/S package is likely to be floated in July 2022. Rs 4500 crore thermal power station brownfield project 870% of erection and installation of BTG works are completed. 8Railway sliding works are in the initial phase of their construction 8RFQ for the C& I system package is likely to be floated in Q3 2022 Rs 900 crore greenfield hydroelectric project 8EIA studies are in progress 8 The hydrology report is yet to be completed. 8Forest clearance stage-1 is pending at the nodal office. 8Civil works package(Lot-1) is expected soon. Rs 800 crore greenfield hydroelectric project : RFQ Ahead 8Bids evaluations are in progress for civil works 8Find out who are the major contenders in the same package 8HM works package expected soon.