Software update: Power projects
Jun 15: Rs 4500 crore greenfield hydroelectric power project
 8Mobilization of equipment is in progress at the site.
 8FC stage-2 is pending at DFO.
 8RFQ for the HM works package is expected soon.
 Rs 8500 crore greenfield hydroelectric power project
 8S/S tender floated and pre-bid meetings are yet to be conducted.
 8Erection and installation of TG units are in progress.
 8RFQ for the 250 KVA P/S works is expected.
 Reconductoring of MePTCL lines: Business opportunities
 8Meghalaya Power Transmission Corporation Ltd (MePTCL) plans to reconductor the existing 132 KV single circuit line with HTLS conductor
 8There are business opportunities ahead
 Old hydel power plant: Business opportunities
 8This hydel power plant is going to complete 25 years of service
 8The owner plans a replacement of old equipment
 8More business opportunities ahead
 Rs 2000 crore greenfield hydroelectric power project 
 8Pilling and foundation works were completed.
 8FC stage-2 is pending at DFO. Detailed engineering works are in progress for P/S works.
 8RFQ for the ACSR moose conductor package is likely to be floated in July 2022.
 Rs 2000 crore greenfield hydroelectric power project 
 8PPA was signed with the government.
 880% of the total land acquisition was completed.
 8EPC package for civil and HM package is expected.
 Rs 323 crore 400 kV SC line to DC line with QUAD Moose ACSR
 8Detailed engineering was completed for S/S.
 8Forest clearance stage is yet to be granted.
 8EPC package for T/L works is likely to be floated in Q3 2022.