Jun 13: Rs 6922 crore greenfield pumped storage project : Civil works package ahead 8DPR is in an advanced stage of approval 8Forest clearence stage-2 is pending at DFO 8PMC package awarded for the same project 8Civil work package(Lot-1) is likely to be floated by Q3 2022 Rs 2990 crore greenfield pumped storage project :Transmission package ahead 8EM package contractor has mobilized the equipment at the site. 8HRT works are in the advanced stage for completion. 8EPC RFQ for power evacuation packages is likely to be floated in August 2022. Rs 2990 crore greenfield hydroelectric power project : PMC Package in Q-3, 2022 8Wildlife clearance (WC) is in progress 8Geotechnical investigation and topographical survey were completed 8PMC package is likely to be floated in the second half of Q3 2022. Rs 730 crore construction of 220 kV S/C transmission line: RFQ ahead 8Detailed engineering works are in progress at the P/S site 8Erection and fabrication works are in progress at the GIS substations. 8ACSR Deer conductor package is likely to be floated (Get in touch with us if you want to know more about these projects)