Jun 03: Rs: 10000 Crores Power Station Replacement Project 8Erection works delayed due to termination of package contracts. 8Contractors hired for the BOP package. Civil works are in progress for the main plant 8DM plant package is expected by July 2022. Rs: 700 Crores Greenfield Hydroelectric Power Project 8Final testing of TRT is in progress 8EM works are in progress 8Transmission line works package Ahead. Rs: 4000 Crores Standalone Pumped Storage Project 8Land acquisition completed 8DPR is yet to grant 8EPC package for main plant works is expected. Rs 2000 crore hydroelectric project: RFQs ahead 8Unfavorable weather condition is a big challenge for the execution of the project. 8Forest clearance is yet to grant. 8Civil works package(Lot-1) is likely to be floated in August 2022. Rs 10000 crore greenfield thermal power plant: C&I package ahead 8Public hearing was completed. 8Contractors has started the mobilization of equipment at the site 8RFQ for the HM works package is likely to be floated in Q3 2022 Rs 300 crore transmission line: An update 8Land acquisition completed 8Erection and installation of S/S work is in progress 8ACSR Moose conductor package is expected. Get in touch with us for more