All content in this website is sourced legitimately

Page No: 1
Software update: Power projects
Jun 03: Rs: 10000 Crores Power Station Replacement Project
8Erection works delayed due to termination of package contracts.
8Contractors hired for the BOP package. Civil works are in progress for the main plant
8DM plant package is expected by July 2022.
Rs: 700 Crores Greenfield Hydroelectric Power Project
8Final testing of TRT is in progress
8EM works are in progress
8Transmission line works package Ahead.
Rs: 4000 Crores Standalone Pumped Storage Project
8Land acquisition completed
8DPR is yet to grant
8EPC package for main plant works is expected.
Rs 2000 crore hydroelectric project: RFQs ahead
8Unfavorable weather condition is a big challenge for the execution of the project.
8Forest clearance is yet to grant.
8Civil works package(Lot-1) is likely to be floated in August 2022.
Rs 10000 crore greenfield thermal power plant: C&I package ahead
8Public hearing was completed.
8Contractors has started the mobilization of equipment at the site
8RFQ for the HM works package is likely to be floated in Q3 2022
Rs 300 crore transmission line: An update
8Land acquisition completed
8Erection and installation of S/S work is in progress
8ACSR Moose conductor package is expected.
Get in touch with us for more


**********************************

Back  |  Top