Software update: Fertilizer projects
Jun 01: Concentrated Nitric Acid Greenfield Project
8Cost: 50 Cr.
8Project EventA consultant is appointed for the preparation of a Detailed Feasibility Report (DFR). The report preparation is still ongoing. RFQ for the LSTK contractor is likely to be released at the end of July 2022, Due to a delay in the DFR preparation.
GSSP/GBSSP/GZSSP/GPG/BSP/BSG Expansion Project
8Cost:48 Cr.
8Project Event: The proposal for the term of references has been granted, the final EIA report preparation is still ongoing. Proposal for environmental clearance is likely to be submitted in Q2 FY 2022-2023. RFQ for the LSTK contractor is likely to be released in Q2 FY 2022-2023.

**********************************