Jan 11: NPK Fertilizer Expansion Project
8Cost: 190 Cr.
8Project Event: The term loans from State Bank of India and Export Import Bank of India have been availed for financing the NPK project. The project has elicited environmental clearance in September 2019, The internal discussion is ongoing. RFQ for the LSTK contractor is likely to be released in Q4 FY 2021.
SSP/NPK Greenfield Project
8Cost:  70 Cr.
8Project Event: Still, the feasibility study are ongoing, The company is planning to submit the proposal for the environmental clearance in Q4 FY 2021. Due to the delay in the feasibility study, RFQ for the contractor is likely to be released after the clearance.

**********************************