All content in this website is sourced legitimately

Page No: 1
Software update: Fertilizer projects
Jun 18: Ammonia-Urea Brownfield Project
8Cost - Rs 6000 crore
8Project Event: RFQ for the Balance Structural Work of Wagon Loading Platform has been out and today is the last date for bid submission. Around 85% of construction work has been completed, Incremental progress during April and May 2021 was 3%. The work has slowed down due to the impact of the second wave of Covid-19.
Officially, this project is meant to be commissioned in December 2021 in place of May 2021. But we think it will stretch right up to Q-1, 2022.
Water Soluble Fertilizer Greenfield Project
8Cost - Rs 200 crore
8Project Event: EIL, FACT Engineering, Mecon and M N Dastrua are in the race  for consultancy services for the preparation of DFR for setting up a Water Soluble Fertilizer (WSF) manufacturing plant, the technical bid has been opened and evaluation is still ongoing. The financial bids are likely to be opened in July 2021. The RFQ for the LSTK contractor is likely to be released in September 2021.

**********************************

Back  |  Top