Jun 03: Ammonia-Urea Energy Saving Project 8Cost - Rs 380 crore 8Project Event: The project is still on hold due to a lack of funds, the project is likely to be activated in July 2021. RFQ for the LSTK contractor is likely to be re-release in Q2 2021 Phosphoric Acid Greenfield Project 8Cost - Rs 10 crore 8Project Event: The proposal has been accepted by SEAC and the proposal for the environmental clearance has been submitted to MOEF in June 2018. The procurement work is ongoing for the contractor and construction is likely to be started in August 2021 due to the second wave of Covid-19.