Software update: Fertilizer projects
Jan 19: Ammonia and Captive Power Unit Greenfield Project  
8Cost - Rs 1920 crore
8Project Event: The project has elicited the terms of references, the final EIA report preparation is likely to be completed in, March 2021. The proposal for the environmental clearance is likely to be submitted in April 2021. RFO for the EPC contractor is likely to be released in Q2 2021
Ammonia-Urea Energy Saving Project   
8Cost - Rs 200 crore
8Project Event: 99.8 % Erection and installation of mechanical equipment have been completed. The pre-commissioning is ongoing, the commissioning is likely to be completed in February 2021.