Software update: Fertilizer projects
Jan 13: Customized Blending Unit for NPK Fertilizer & Ammonia Storage Tank Greenfield Project  
8Cost - Rs 90 crore
8Project Event: The project is on hold due to the company's internal issues. It is likely to activate in Q1 2021. RFQ for the Contractor is likely to be released in Q1 2021
NPK-SSP & Sulphuric Acid Expansion Project  
8Cost - Rs 15 crore
8Project Event: RFQ for a contractor is likely to be released after the environmental clearance. The public hearing has been completed but environmental clearance is due and valuation is ongoing, It is likely to be elicited at the end of Jan 2021 in place of December 2020. RFQ for the EPC contractor is likely to be released in February 2021.


**********************************