Software update: Fertilizer projects
Jan 12: DAP Greenfield Project   
8Cost - Rs 200 crore
8Project Event: The proposal for the term of references has been accepted and studies are still ongoing, and the proposal for the environmental clearance is likely to be submitted in February 2021. The company has applied for a loan, RFQ for the EPC contractor is likely to be released in March 2021.
Sulphuric Acid Expansion Project  
8Cost - Rs 100 crore
8Project Event: The company has been signed up  Furnace Fabrica as an EPC contractor, all the equipment has reached the site. 99 % of construction work has been completed. The pre-commissioning is ongoing, commissioning is likely to be completed in Q1 2021.