Jan 12: DAP Greenfield Project 8Cost - Rs 200 crore 8Project Event: The proposal for the term of references has been accepted and studies are still ongoing, and the proposal for the environmental clearance is likely to be submitted in February 2021. The company has applied for a loan, RFQ for the EPC contractor is likely to be released in March 2021. Sulphuric Acid Expansion Project 8Cost - Rs 100 crore 8Project Event: The company has been signed up Furnace Fabrica as an EPC contractor, all the equipment has reached the site. 99 % of construction work has been completed. The pre-commissioning is ongoing, commissioning is likely to be completed in Q1 2021. Click on Details for more.