All content in this website is sourced legitimately

Page No: 1
Software update: Fertilizer projects
Mar 26: Ammonia-Urea Greenfield Project 
8Cost - Rs 5500 crore
8Project Event: The project is in initial stage, and the company is still studying the feasibility study/DPR. The company said that firstly they will do the Phos acid expansion project, but the hiring of contractor for the Ammonia-Urea project is likely to completed within year. RFQ for the PMC is likely to be release in June 2020.
Click here for more details
Urea Expansion Project
8Cost - Rs 52 crore
8Project Event: Final EIA report preparation is ongoing, They are planning to releasethe RFQ for the Process Licensor in May 2020. RFQ for the LSTK contractor is likely to be released in June 2020.
Click here for more details
(
Available through www.indianfertilizer.com)


**********************************

Back  |  Top