Mar 18: Ammonia Greenfield Project 8Cost - Rs 2773 crore 8Project Event: The project is likely to be submitted for environmental clearance in April 2020. The company needs Rs 600 to 700 crore addition capex which is still under process. The RFQ for the contractor is likely to be released in April in place of March 2020 due to a delay in capital approval as well as protracted internal discussions. Click here for more details NPK-TSP-GSSP Greenfield Project 8Cost - Rs 100 crore 8Project Event: The proposal for the term of references has been granted for environmental clearance and the proposal for the environmental clearance is likely to be submitted in April 2020. RFQ for the EPC contractor is likely to be released in April 2020. Click here for more details.