Software update: E&P projects
Mar 17: 8Project Name: Shipahijala Exploratory Drilling
8Project Cost: Rs 2850 crore
8Project Event: RFQ for the hiring of an EIA consultant is expected by June 2020 instead of March
Similarly RFQ for the hiring of seismic survey services is expected by Q3 2020.
Click here for more details

8Project Name: Aliabet Oil Field Development
8Project Cost: Rs 156.4 crore
8Project Description: Oil and Natural Gas Corporation Limited's is expected to release the RFQs for the hiring of EPC contractor for the laying of a 4" diameter 35 km test line along with the laying down of flowlines for connecting with the 6" diameter 35 km common trunk line from the Aliabet field to the CTF Ankleshwar by May 2020.
8Project Event: RFQs for hiring of EPC contractor is expected by June 2020 now
Click here for more details

8Project Name: Dholasan Oil Field Development
8Project Cost: Rs 200 crore
8Project Description: Gujarat Natural Resources Limited is expected to release the RFQs for the hiring of equipment for its marginal field Dholasan by May 2020.
Click here for more details


**********************************