Jan 16: Effluent Treatment Plant Up-gradation Project 8Cost - Rs 101 crore 8Project Event: The NIT for the LSTK contractor is likely to be re-released in late January 2020 in place of Dec 2019 due to a delay in the board approval and technical issues. Click here for more details Urea Casale Revamp Project 8Cost - Rs 137 crore 8Project Event: The project has been delay by three months due to procurement issues, as all long lead item has not reached the site. The company is planning to revamp the urea plant in the upcoming shut down in April 2020. Click here for more details (Available only through www.indianfertilizer.com)