Software update: Fertilizer projects
Jan 09: NPK Fertilizer Expansion Project
8Cost - Rs 190 crore
8Project Event: The project has been elicited the environment clearance in September 2019, RFQ for the EPC contractor is likely to be released in February 2020 now while earlier it was meant to come out in December.
Click here for more details
Sulphuric Acid Expansion Project
8Cost - Rs 100 crore
8Project Event: The project has been commissioned and RFQ for the sulphur is likely to be released in February 2020.
Click here for more details
(
Available only through www.indianfertilizer.com)


**********************************