Software update: Fertilizer projects
Jan 08: DAP Expansion Project
8Cost - Rs 100 crore
8Project Event: The project is waiting for environmental clearance. It takes a minimum of three to four months. RFQ for the EPC contractor is likely to be released in March 2020. The company is planning to complete its Phosphoric acid expansion first, for which construction has been started.
Click here for more details
Phosphoric Acid Expansion Project
8Cost - Rs 1100 crore
8Project Event: The Company has selected Jacob for the EPCM contractor and the RFQ for the long lead item are being released one by one.  One RFQ for the Rotray Dryers & Tanks has been released and another RFQ for the Cyclone system & Air Pollution control system is likely to be released byt the end of January 2020. Construction is likely to be started in February 2020 as there seems to have been a delay in procurement work.
Click here for more details
(Available through www.indianfertilizer.com)

**********************************

Back  |  Top