Rs 400 crore Drilling Field Exploration: Work coming up
Jul 09: 8Project Name: Drilling Field Exploration
8Project Cost: Rs 400 crore
8Project Description: Oil And Natural Gas Corporation Limited has reapplied for the TOR of the 10 well exploratory programme in a PML block, seeking the extension of the Original TOR. In the meanwhile, the EIA consultant will be hired once the TOR for the project is granted approval. The drilling rig to be utilized for the project is already available in the adjacent block where drilling is already going on.
8Project Event: RFQ for hiring EIA services is expected by Q4 2019
RFQ for hiring rig mobilization services is expected by Q3 2020
RFQ for the supply of oilfield chemicals is expected by Q3 2020
8Expenditure Approval: Q1/2017
8RFQ Date: Q4/2019
8Release Date: Q4/2019
8Start Date: Dec/2020
8Completion Date: Dec/2020