Software updates: Power projects
May 20: Project Name: Guru Hargobind Thermal Power Plant - Installation of FGD
8Project Cost: 400 crores
8Project Description: Punjab State Power Corporation Limited along with consultant NTPC has prepared the technical specifications for installation of wet limestone based flue gas desulphurisation system in the operating 920 MW (2x210+2x250 MW) thermal power plant located in the Lehra Mohabbat district of Punjab.
8Project Event: RFQ for design, engineering, supply, transportation, installation, erection, and completion of an FGD package is expected by July 2019.
8Expenditure Approval: Q1:2018
8RFQ Date: Jul/2019
8Release Date: Jul/2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Suratgarh Thermal Power Station - FGD Addition
8Project Cost: 300 crores
8Project Description: Rajasthan Rajya Vidyut Utpadan Nigam Limited along with consultant Fichtner Consulting Engineers Limited is carrying out investigations in order to clarify whether to install an FGD system or a DSI system in its operating 1500 MW (6x250 MW) Thermal Power Station at Suratgarh, in Sri Ganga Nagar district of Rajasthan. Meanwhile, tenders are ongoing for the 2x660 MW under- construction Suratgarh supercritical thermal power project. 
8Project Event: RFQ for design, supply, installation, and commissioning of an FGD is expected to be out by the Q4 2019.
8Expenditure Approval: Q3:2017
8RFQ Date: Q4:2019
8Release Date: Q4:2019
8Start Date: 2022
8Completion Date: 2024
Click here for more details

Project Name: Gas Based Combined Cycle Expansion Power Project
8Project Cost: 3500 crores
8Project Event: RFQ for an EPC contractor for the main plant works is expected by the August 2019.
8Expenditure Approval: Q3:2019
8RFQ Date: Aug/2019
8Release Date: Aug/2019
8Start Date: Q3:2020
8Completion Date: Q4:2023
Click here for more details

Project Name: Tanda Thermal Power Expansion Project
8Project Cost: 10000 crores
8Project Description: National Thermal Power Corporation Limited along with ESP contractor BHEL is carrying out erection works for the 1320 MW (2x660 MW) super-critical thermal power expansion project at its existing facility, where a 440MW plant was installed, at Tanda Thermal Power Station. 
8Project Event: RFQ for limestone handling plant and gypsum handling unit for the FGD system is expected by the Q3 2019.
8Expenditure Approval: Sep/2014
8RFQ Date: Q3:2019
8Release Date: Q3:2019
8Start Date: Oct/2015
8Completion Date: Q4:2019
Click here for more details

Project Name: Shree Singaji Super-Critical Thermal Power Brownfield Project (Stage-II)
8Project Cost: 7500 crores
8Project Description: Madhya Pradesh Power Generating Company Limited is carrying out the price bid evaluation of an EPC contractor for the FGD system package for the 1320 (2x660 MW) super-critical brownfield thermal power complex at the existing 1200 MW (2x600 MW) facility located at the Dongalia village, in the Khandwa district of Madhya Pradesh. L&T, GE Power India, Mitsubishi Hitachi Power Systems India Pvt Ltd, Doosan Power Systems India Pvt Ltd, and ISGEC Heavy Engg. Ltd are the major contenders in the race. 
8Project Event: The award of the FGD system package is expected by June 2019.
8Expenditure Approval: 2014
8RFQ Date: Jun/2019
8Release Date: Jun/2019
8Start Date: 31/Dec/2014
8Completion Date: Q4:2019
Click here for more details


**********************************