OIL's Rs 2000 crore programme delayed
Apr 15: 8Project Name: Oil and Gas Field Site Development
8Project Cost: Rs 1988 crore
8Project Description: Oil India Limited's 54 well development drilling programme and pipeline installation project, under Tinsukia PML, Tinsukia Extension PML and Chabua PML blocks in Assam has been delayed. Know more about it
8Project Event: RFQ for hiring Rigs and other equipment is expected by Q4 2019
 RFQ for hiring an EPC contractor for the production facilities and pipeline network is expected by Q4 2019
8Expenditure Approval: Q3/2017
8RFQ Date: Q4/2019
8Release Date: Q4/2019
8Start Date: Q2/2020
8Completion Date: Q4/2021