Apr 11: 8Project Name: Effluent Pipeline
8Project Cost: Rs 100 crore
8Project Description: Oil and Natural Gas Corporation Limited is soon expected to float a tender for a third party inspection (TPI) agency for Nawagam Ramol Effluent pipeline. Currently, the technical bid evaluation for the hiring of LSTK contractor is going on and is expected to be finished by the end of this month. Furthermore, the LOI will be issued in May 2019. At least 4 to 5 potential bidders are believed to have bid for the project. 
8Project Event: RFQ for the TPI is expected by June 2019.
8Expenditure Approval: Jan/2019
8RFQ Date: Jun/2019
8Release Date: Aug/2019
8Start Date: Aug/2019
8Completion Date: Apr/2021