Apr 09: Ammonia - Urea & Captive Power Plant Greenfield Project 8Cost - Rs 10000 crore 8Project Event: The project is on hold for one month. Activity is likely to be started in June 2019. Click here for more details Ammonia-Urea Energy Saving Project 8Cost - Rs 217 crore 8Project Event: The project has signed all the agreement with Siemens for the long lead item and delivery is ongoing. The erection is ongoing at the site, the project is likely to be commissioned in Nov 2019. Click here for more details