Apr 05: H-Energy seems to be hard at work to complete the vital 60-km link between its FSRU at Jaigarh to GAIL's tie-in points to its trunk pipelines.
8During a PNGRB Regulation 16 meeting, much to the consternation of PNGRB officials, H-Energy executives refused to commit to a deadline for a mechanical completion date for the pipeline, and even though another six months was given by the regulator, it looks unlikely that the pipeline will be constructed by then
8The pipeline is encountering ROW problems and GAIL is also reportedly playing truant in working out the tie-in details
8So, what is the realistic deadline for completion of the pipeline?